Portfolio Overview
Loading Data...
Fetching the latest information
Fetching the latest information
Independent POC workspace • 208-project reference dataset across 5 business units • not connected to live operations
Across Farm, Feed, Food & Swine
Contract sum incl. active VO claims
Civil, Electrical & Piping specialists
Weighted by site deliverables
Demonstrates proposed insights using the checked-in reference dataset; no live RAG process is running.
Identified stalled progress and environmental disruption on site. Specifically, project CE-104 (Desaru Farm Sector) reported an "Emergency repair due to Windstorm" causing significant structural delay.
To mitigate delays before the upcoming rainy season, recommend reallocating civil works contractor Pioneer from Desaru Block 1-8 (near 100% completion) directly to Block 9-16 to accelerate finishing timeline.
| Project ID | Project Name | Business Unit | Location | Contractor | Progress % | Contract Value (RM) |
|---|---|---|---|---|---|---|
| CE-001 | Capacitor Bank An Xin Target 500RM TNB Bill reduce each month | Food | An Xin Kepong | NKM | 100% | RM 6,000 |
| CE-002 | Water Supply 2inches PVC pipe est.50m | Farm | BRC2 | Kasas Plumbing | 100% | RM 10,500 |
| CE-003 | Broilers 2houses 18x95x2.7m Finish 15/01/25 | Farm | BRC2 | MKR | 100% | RM 1,250,000 |
| CE-004 | Broilers 1houses 16x120x2.7m Finish 15/01/25 | Farm | BRC5 | LLK | 100% | RM 645,000 |
| CE-005 | CCTV BIN Monitoring, 32 unit transport | Feed | BWF | Zheng Cheng | 100% | RM 63,404 |
| CE-006 | CYF earthwork | Swine | Chau Yang Farm | LNL Ent (Liew Eric) | 100% | RM 430,000 |
| CE-007 | Repairing Crack/ Big Gap Area Block 1 to Block 8 at Layer | Farm | Desaru | Pioneer | 100% | RM 18,000 |
| CE-008 | Repairing Crack/ Big Gap Area Block 9 to Block 16 at Layer | Farm | Desaru | Pioneer | 100% | RM 19,900 |
| CE-009 | Replace door and add urinal partition | Farm | Desaru | Pioneer | 100% | RM 19,810 |
| CE-010 | Emergency repair due to Windstorm | Farm | Desaru | Pioneer | 100% | RM 177,032 |
| CE-011 | Fencing Manager House 91m | Farm | Desaru | Southline Engineering | 100% | RM 28,800 |
| CE-012 | Egg bay (liquid) | Farm | Desaru | Pioneer | 100% | RM 15,589 |
| CE-013 | OVERHAUL SERVICE & MAINTENANCE BIOGAS GENSET 1x600 kVA + New 12x Cylinder heads Assy | Farm | Desaru | Advance Energy | 100% | RM 50,000 |
| CE-014 | Desaru2 Survey | Farm | Desaru2 | Mesra Ukur | 100% | RM 35,640 |
| CE-015 | Water Tank 5,000 GL 4x4m2 Tank 48% Concrete 52% | Farm | Kluang Hatchery | South Line Eng. | 100% | RM 22,400 |
| CE-016 | Road repair | Farm | Kluang Hatchery | South Line Eng. | 100% | RM 23,820 |
| CE-017 | Tubewell 12m3/hr Groundfos SP11-24 Motor MS4000 3phases | Farm | Kluang Farm | MILLENIUM | 100% | RM 76,000 |
| CE-018 | Solar roof 400kwp saving 115,000RM/year | Farm | Kluang Hatchery | Solarvest | 100% | RM 50,000 |
| CE-019 | Supply and install U drain 52m | Farm | Kluang Hatchery | You Fatt | 100% | RM 140,000 |
| CE-020 | Renovation Hostel 12rooms | Farm | Kota Farm | Pioneer | 100% | RM 245,000 |
| CE-021 | Change PU Roofing Pedas 2 For House 3 Flock C 1,680m2 PK3 4house move from Pedas 2 by MKR cost 237,500RM | Farm | Kota Farm | Pioneer | 100% | RM 45,200 |
| CE-022 | Kota TNB ( KM & BP for TNB only) 1,000A | Farm | Kota Hatchery | TSK Enterprise | 100% | RM 21,600 |
| CE-023 | Kota hatchery earthwork | Farm | Kota Hatchery | SZ Bumi | 100% | RM 119,500 |
| CE-024 | Move and renovate Water treatment Tank from Pedas 2 to PK3 | Farm | PK3 | BMS | 100% | RM 50,500 |
| CE-025 | Add on packaging room (3.6m x 20m) | Farm | PK3 | Kowitech | 100% | RM 32,800 |