This project is seeded from standard construction progress claim models (dummy/*.csv& reference billing templates) to demonstrate multi-workspace executive roll-ups, comparative KPI tracking, and portfolio-wide analytics.
123 activities across the SOVO and SOHO towers, scheduled from 1 April 2026 to 30 December 2029. Actual progress and total float were not supplied, so the app presents baseline timing separately from validated delay.
| Item | Milestone Completion | Commencement Date | Target Completion Date | Status |
|---|---|---|---|---|
| 1 | Completion of Mock Up Unit | 12-Jul-2026 | 10-Oct-2026 | In Progress |
| 2 | Completion of TNB Substations | 01-Apr-2026 | 30-Jun-2026 | Completed |
| 3 | Completion Sewerage Connection | 01-Nov-2026 | 30-Jan-2027 | On Schedule |
| 4 | Completion of Water Reticulation Works | 01-Jan-2027 | 01-Apr-2027 | Planned |
| 5 | PDI (Pre-Delivery Inspection) | 01-Oct-2027 | 30-Dec-2027 | Planned |
Detailed breakdown modeling both the financial weightage per unit and live site completion updates based on standard construction tracking models.
No manpower data available for this period.
TNB Substation delay (target Jun 2026) may trigger M&E works deferment. Projected 3-week downstream impact on electrical first fix across all floors.