Registered client baseline · Hallson KLCC123 activities · 01 Apr 2026 to 30 Dec 2029 · CSV and MS Project XML counts reconciled
Reference-backed
Baseline activities123
122 linked to predecessors
Baseline elapsed12%
Calendar proxy at 12 Sep 2026
Project / tower4
3 towers · Tower A SOVO · Tower B SOVO · Tower C SOHO
Actual progress / total floatNot supplied
Upload the next status programme
Programme baseline30 Dec 2029
Illustrative construction baseline 01 Apr 2026 to 30 Dec 2029
Planned finish passed4
Needs status confirmation, not labelled delayed
Planned in progress3
At the fixed POC review date
Source assumptions / notes26
Visible beside affected activities
Activity mix by discipline
All 123 baseline activities from the supplied register.
Preliminaries4 activities
3%
Structural27 activities
22%
Architectural47 activities
38%
M&E37 activities
30%
Handover6 activities
5%
General2 activities
2%
Baseline control dates
Dates shown exactly from the programme register.
Notice to proceed / contractual commencementKLCC link walkway: interfaces, approvals and third-party consentsCore and slab cycle: nominal level band 71-roofScreed, ceiling, second fix and fit-out: band 8Site-wide integrated M&E, life-safety and utility testingPractical completion and handover by contractual deadline
What Aibimz has readActivity IDs, work fronts, baseline dates, working durations, predecessor IDs and source notes.
What the next update must addStatus date, actual start/finish, current progress, remaining duration, total float and critical-path state.
Data boundary: the supplied CSV and XML files provide baseline activities, dates, working durations and predecessor IDs. They do not provide a current status date, verified actual progress, total float or critical-path flags. Baseline timing prompts review; it does not prove delay.