Historical MPP snapshot · registered as comparison baselineUpdated 1 Jan 2023 · 3,790 activities · source WBS uses Block D and Block E · planned finish 30 Sep 2024
Pilot source
Planned progress proxy43%
Time elapsed at 1 Jan 2023
Recorded snapshot13%
MPP custom field “Draft %”
Management alerts9
Rule-based POC flags
Concept spatial mapping · demo statusThe project image and level selection demonstrate the proposed navigation. Package percentages remain Block-level MPP snapshot values—not Level 5 site actuals.
Illustrative digital-twin view
Selected blockOther block
Data boundary: programme dates, task IDs, total float, critical flags and “Draft %” values are extracted from the supplied MPP. Planned progress is a time-elapsed proxy. Revision-comparison update values and spatial mapping remain clearly marked illustrative until a genuinely later MPP and verified site data are connected.