AIBIMZ Industrial Infrastructure Development · 185 acres · Reporting date 31 Aug 2026
| Activity | Plan | Completed | Remaining | Progress |
|---|---|---|---|---|
| Site clearing | 185 acres | 170 acres | 15 acres | 92% |
| Topsoil stripping | 215,000 m³ | 198,000 m³ | 17,000 m³ | 92% |
| Cut excavation | 650,000 m³ | 276,000 m³ | 374,000 m³ | 42% |
| Filling | 460,000 m³ | 152,500 m³ | 307,500 m³ | 33% |
| Imported fill | 95,000 m³ | 38,000 m³ | 57,000 m³ | 40% |
| Disposal | 285,000 m³ | 106,000 m³ | 179,000 m³ | 37% |
| Rock excavation | 18,000 m³ | 4,500 m³ | 13,500 m³ | 25% |
Test the daily verified output required to clear the sample balance. This scenario does not change the source data.
| Item | Scope | Current / verified | Sample value | Readiness |
|---|---|---|---|---|
| Site clearingE1.01 | 185 acres | 170 / 170 | RM 1,275,000 | Ready |
| Cut excavationE1.02 | 650,000 m³ | 85,000 / 78,500 | RM 942,000 | Review |
| FillingE1.03 | 460,000 m³ | 62,000 / 56,000 | RM 1,120,000 | Review |
| Earth drainD2.01 | 4,200 m | 850 / 790 | RM 316,000 | Pending inspection |
| Road sub-baseR3.01 | 18,500 m² | 3,600 / 3,250 | RM 227,500 | Ready |