Site Delivery
Earthwork & Infrastructure
Interactive POCLoading project information
AIBIMZ Industrial Infrastructure Development · 185 acres · Reporting date 31 Aug 2026
| Package | Location | Plan / Actual | Status | |
|---|---|---|---|---|
| Main access roadINF-01 | CH0+000–1+600 | 45% / 38% | Behind | |
| Earth drainINF-02 | CH0+000–0+500 | 100% / 85% | Behind | |
| Box culvert BC01INF-03 | CH0+850 | 70% / 70% | On track | |
| Road sub-baseINF-04 | CH1+000–1+600 | 60% / 42% | Delayed | |
| Sewer reticulationINF-05 | Zone C | 35% / 30% | Behind | |
| Water reticulationINF-06 | Zone D | 25% / 28% | Ahead | |
| Utility ductINF-07 | Zone E | 40% / 48% | Ahead | |
| Retaining wall RW01INF-08 | Zone B | 55% / 50% | Behind |