Registered client baseline · ATS Kajang102 activities · 01 Apr 2026 to 30 Dec 2027 · CSV and MS Project XML counts reconciled
Reference-backed
Baseline activities102
101 linked to predecessors
Baseline elapsed26%
Calendar proxy at 12 Sep 2026
Site / zone7
6 zones · 108 Semi-D factory units
Actual progress / total floatNot supplied
Upload the next status programme
Programme baseline30 Dec 2027
Construction baseline 01 Apr 2026 - 30 Dec 2027
Planned finish passed11
Needs status confirmation, not labelled delayed
Planned in progress5
At the fixed POC review date
Source assumptions / notes1
Visible beside affected activities
Activity mix by discipline
All 102 baseline activities from the supplied register.
Preliminaries10 activities
10%
Structural31 activities
30%
Architectural12 activities
12%
M&E28 activities
27%
Handover14 activities
14%
General7 activities
7%
Baseline control dates
Dates shown exactly from the programme register.
Commencement and possession milestoneZone release and detailed setting outWalling, windows and external envelopeDoors, shutters, finishes and paintingSite-wide fire, utility and integrated systems testsContract completion: 108 semi-D units
What Aibimz has readActivity IDs, work fronts, baseline dates, working durations, predecessor IDs and source notes.
What the next update must addStatus date, actual start/finish, current progress, remaining duration, total float and critical-path state.
Data boundary: the supplied CSV and XML files provide baseline activities, dates, working durations and predecessor IDs. They do not provide a current status date, verified actual progress, total float or critical-path flags. Baseline timing prompts review; it does not prove delay.